| Client: |
MoD Germany |
 |
 |
| Requirement: |
Temporary catering facilities to feed 500 men during 42 months of the planned refurbishment of two kitchens and dining halls at York and Oxford Barracks, Munster |
|
 |
PKL provided: |
The turnkey package including design, installation and maintenance of a 500 man Portable Kitchen with a dining hall for 250. The PKL's unique open plan kitchen design, Transworld Kitchen, was used |
|
 |
| Project features: |
The key feature of the project was the requirement for relocation of catering facilities from York Barracks to Oxford Barracks after 28 days. This is a feat that PKL project management achieved whilst at the same time providing all lead up services, foundations and site works |
|
 |