PKL Group Project Case StudiesExample of PKL Foodservice ProjectsTemporary Replacement Service Station
PKL supplied a service station chain requiring an entire replacement facility
PKL provided a temporary kitchen to a leading service station chain.
Circumstances: The existing facility had been totally destroyed by fire and would take 12 months to rebuild
Reason For Hire: To ensure minimum possible break in business, the service station required a temporary solution that would incorporate all the existing areas of the service station
Requirements: PKL supplied a toilet facility, a shop, and a temporary dining and catering facility
Solution: The facility was delivered, installed and operational whilst the new facility was built
Time-scale: This facility was operational 3 weeks from the initial phone call, ensuring the minimum possible break in business