© Copyright PKL Group All rights reserved
| |
 |
|
 |
|
Portable Kitchen at Middle Temple
|
PKL's experience of using Portable Kitchens allowed Middle Temple to continue catering during a refurbishment. The location of Middle Temple Great Hall, the age of the building and surrounding buildings meant PKL had to overcome a number of site restrictions including weight sensitive lanes and restricted space.
 The complexity of the project meant months of site assessments and design drafts to allow for a workable facility in this location. The only way to construct a facility using mobile kitchens to meet all the catering needs and site requirements was to build upwards.
It was the first project of this type for PKL and the final design comprised a 4-level, 8 unit stacked system using ISO Portable Kitchens.
 A link into the service areas of the Great Hall was incorporated and deliveries to each level of the facility were achieved by means of a hoist on one side of the gantry. A staircase was also built alongside the units to provide access to other levels.
The Great Hall stands amongst many other buildings in a small lane, PKL devised a carbon filtration extraction system that ensured any escaping grease or fumes would be caught preserving the buildings and immediate environment.
 "No other company could have designed and installed this facility and maintained such professionalism throughout every stage of a project like this. PKL are a pleasure to work with."
Colin Davidson Catering Manager, Middle Temple

| Overview |
| |
| Size |
|
196m² |
| Covers |
|
900 per day |
| Programme of works |
|
3 weeks |
| Reason for hire |
|
Refurbishment |
| Features of hire |
|
8 unit stacked facility |
|
|
For more information contact our hire team on 0845 840 4242 or e-mail hiresales@pkl.co.uk
|
|
 |
|
 | |
|
|